Road Resurfacing: Fillmore St., 72nd Ave. to 48th Ave., Allendale/Blendon Twps., begins May 20, 2024

START DATE: Week of May 20, 2024

ESTIMATED FINISH: Late May/Early June

WHERE: Fillmore St., 72nd Ave. to 48th Ave., Allendale Twp.

WHY: Road Resurfacing

BACKGROUND: Beginning the week of May 20, 2024, contractors for the Ottawa County Road Commission will begin a resurfacing project on Fillmore St. from 72nd Ave. to 48th Ave. in Allendale Twp.

This project will consist of milling down the existing asphalt, adding a paved shoulder for a new road width of 30’, resurfacing the road with new asphalt, and gravel shoulder restoration.

This project is expected to last through late May/early June 2024, however all work is weather dependent and completion dates are subject to change.

TRAFFIC IMPACT: The road will remain open to through traffic, however traffic will be maintained using temporary lane closures under flag control during work hours. Be prepared for possible delays when traveling through this area during project hours.