Quincy St. in Holland Twp. to close July 6 for culvert, resurfacing work

Road Closure - Quincy St. - 96th to 120th

WHEN: July 6-30, 2021

WHERE: Quincy St., between 120th Ave. and 96th Ave., Holland Twp.

WHY: Culvert Replacement/Cold Milling/HMA Resurfacing

BACKGROUND: The Ottawa County Road Commission will close Quincy Street between 120th Avenue and 96th Avenue in Holland Township beginning Tuesday, July 6, 2021, for a culvert replacement, cold milling, and HMA resurfacing with the addition of 4-foot paved shoulders on Quincy St. between 120th Ave. and 96th Ave.

The project is expected to be completed by July 30, but please note that all dates are tentative and work is weather dependent.

DETOUR: The planned detour for this project is 96th Ave./Riley St./120th Ave.


CSX planning multiple crossing repairs in Georgetown Twp. area

The Ottawa County Road Commission has been notified that CSX Railroad is scheduled to reconstruct their railroad grade crossings at the following locations and dates:

  • Cottonwood Drive north of M-121 (Georgetown Township) – 7/6/21
  • 12th Avenue north of M-121 (Georgetown Township) – 7/7/21
  • School Avenue north of M-121 (City of Hudsonville) – 7/7/21
  • 40th Avenue north of M-121 (City of Hudsonville) – 7/8/21

The above locations will be completely closed off to traffic at the crossing starting on the listed dates and are expected to each be closed for up to four days.

Signed detours will be provided for all closures.

Road Closures:

TOWNSHIPSTREETSEGMENTREASONRESPONSIBLE
AUTHORITY
EST.
DURATION
Port SheldonBlair St.152nd Ave. to 144th Ave.Culvert ReplacementOCRCSept. 18-Oct. 6
Blendon96th Ave.Port Sheldon St. to Tyler St.Culvert ReplacementOCRCSept. 18-27
AllendaleFillmore St.72nd Ave. to 96th Ave.Culvert ReplacementOCRCSept. 18-26
Allendale52nd Ave.Fillmore St. to Pierce St.Sanitary SewerPermitAug. 14-Oct. 13

Road Resurfacing:

TOWNSHIPSTREETSEGMENTEST. DURATION
Zeeland64th Ave.Byron Rd. to Chicago Dr.Sept. 5-28
Holland144th Ave.Shadybrook Dr. to Riley St.Aug. 21-Sept. 22
Holland8th St./Chicago Dr.U.S. 31 to City LimitsJuly 10-Nov. 1

Note: Resurfacing does not close the road. It will remain open to through traffic, with temporary lane closures.