40th Ave. reconstruction begins Monday, Aug. 3, in Jamestown Twp.

WHAT: Gravel Road Reconstruction

WHERE: 40th Ave.

TOWNSHIP: Jamestown

START DATE: Monday, August 3, 2020

ESTIMATED COMPLETION DATE: Friday, October 2, 2020

PROJECT DETAILS: The Ottawa County Road Commission, in conjunction with Jamestown Township, will be reconstructing 40th Avenue from the county line to Adams Street. The existing gravel road will be reconstructed to a paved road.

The project is expected to begin on Monday, August 3, and be completed by Friday, Oct. 2. Note that all dates are tentative, and work is weather-dependent.

TRAFFIC IMPACT: 40th Avenue will be closed to through traffic between the county line and Adams Street during this project, with access being maintained for those living within the construction limits.

28th Ave. to close from Baldwin St. to Bauer Rd. in Georgetown Twp. Aug 3-14

WHAT: Road Closure

WHERE: 28th Ave., Baldwin St. to Bauer Rd.

TOWNSHIP: Georgetown

START DATE: Monday, August 3, 2020

ESTIMATED COMPLETION DATE: Friday, August 14, 2020

PROJECT DETAILS: 28th Avenue in Georgetown Township will be closed between Baldwin Street and Bauer Road Aug. 3-14 for permitted water crossing work.

Note that all dates are tentative, and work is weather-dependent.

Road Closures:

Township: Road: Segment: Work: Est. Finish:
Tallmadge Luce/Linden St. M-45 to 20th Ave. Bank Erosion Repair TBD
Georgetown 48th Ave. North of Fillmore St. Cross Culvert Aug. 7
Allendale/Polkton 68th Ave. Leonard St.-M-45 Bridge Rehab Aug. 14
Holland Lakewood Blvd. River Ave. Intersection Water Main Aug. 7
Allendale 68th Ave. At Pingree St. Cross Culvert Aug. 7
Georgetown 28th Ave. Baldwin St. to Bauer Rd. Water Crossing Aug. 14
Jamestown 40th Ave. Adams St. to county line Reconstruction Oct. 2
Georgetown Port Sheldon St. 40th Ave. to 48th Ave. Reconstruction Oct. 23

 

Street Resurfacing:

Township:  Road: Segment: Est. Finish:
Grand Haven Lakeshore Dr. Rosy Mound Dr. to Buchanan St. Aug. 10
Georgetown 14th Ave./Port Sheldon St. 44th St. to Main St. Aug. 15
Jamestown Riley St. 32nd Ave. to 8th Ave. Aug. 15
Jamestown Adams St. 48th Ave. to 24th Ave. Aug. 15

Subdivision Street Resurfacing:

Township: Est. Finish:
Holland August 14

Upcoming Construction Projects:

Township:  Road: Segment: Work: Est. Start:
Jamestown Adams St. 48th Ave. to 24th Ave. Resurfacing Late July

Note: Resurfacing does not close the road. It will remain open to through traffic, with temporary lane closures.