Read below to find out all about our current and upcoming construction projects, and road closures.
You’re encouraged to log on to our website where you can view a list of all of our upcoming construction projects, see our interactive road work map and check current road and bridge closures.
You can also visit our Facebook and Twitter pages for up-to-date Road Commission information.
2021 cape seal program continues July 12th
Crews will be returning the week of July 12 to start the second phase of our cape seal surfacing work.
Contractors will be conducting the microsurfacing portion of the cape seal project, in which a thin layer of slurry is applied over the chip sealed roadway.
Per the contractor, their tentative plan is to start Monday, July 12, on Port Sheldon St. between U.S. 31 and Butternut Drive.
From there, the tentative schedule is as follows:
Tuesday 7/13
136th Avenue from Quincy to Port Sheldon
Wednesday 7/14
48th Avenue from Chicago Drive to Port Sheldon
Thursday 7/15
48th Avenue from Port Sheldon to Bauer
Friday 7/16
Bauer from 24th Avenue to 48th Avenue
Crews will then return on Tuesday, July 20, to complete any outstanding work.
Please note that all work is weather dependent, and this schedule is subject to change.
Lincoln St. at 68th Ave. to close July 12-14
WHEN: July 12-14, 2021
WHERE: Lincoln St. at 68th Ave., Allendale Twp.
WHY: Culvert Replacement
BACKGROUND: The Ottawa County Road Commission will close Lincoln Street at 68th Ave. in Allendale Township beginning Monday, July 12, 2021, for a culvert replacement.
The project is expected to be completed by July 14, but please note that all dates are tentative and work is weather dependent.
DETOUR: The planned detour for this project is 68th Ave. to Warner St. to 64th Ave.
Road Closures:
TOWNSHIP | STREET | SEGMENT | REASON | RESPONSIBLE AUTHORITY | EST. DURATION |
---|---|---|---|---|---|
Jamestown | 16th Ave. | Riley St. to Greenly St. | Sanitary Sewer | Permit | June 28-July 15 |
Holland | N. State St. | Riley St. to Roosevelt Ave. | Storm Sewer | Permit | June 20-27 |
Park | 160th Ave. | At Lakewood Blvd. | Water Main More Info | Permit | June 4-25 |
Georgetown | 28th Ave. | North of Fillmore | Reconstruct | Permit | May 24-June 30 |
Jamestown | Greenly St. | 16th Ave. to 24th Ave. | Sanitary Sewer | Permit | May 23-June 30 |
Zeeland | 84th Ave. | Adams St. to Gordon St. | Sanitary Sewer | Permit | April 6-June 30 |
Holland/Park | Lakewood Blvd. | 160th Ave. to N. River Ave. | Water Main More Info | Permit | March 18- August |
Grand Haven | 160th Ave. | Ferris St. to Lincoln St. | Water Main | Permit | March 10-July 31 |
Road Resurfacing:
TOWNSHIP | STREET | SEGMENT | EST. DURATION |
---|---|---|---|
Zeeland | 24th Ave. | 96th Ave. to 72nd Ave. | July 5-20 |
Crockery | 144th Ave. | Leonard St. to Apple Dr. | June 16-30 |
Note: Resurfacing does not close the road. It will remain open to through traffic, with temporary lane closures.