Weekly Construction Update: Sept. 9, 2022

Read below to find out all about our current and upcoming construction projects, and road closures for the upcoming week.

View a list of all of our upcoming construction projects, see our interactive Infrastructure Project Dashboard and check current road and bridge closures.

You can also visit our Facebook and Twitter pages for up-to-date Road Commission information.

Permitted closure of Lakeshore Dr. in Park Twp. begins Sept. 12

WHEN: Sept. 12-Oct. 24

WHERE: Lakeshore Dr., Quincy St. to Riley St., Park Twp.

WHY: Pedestrian Bridge Construction

BACKGROUND: A permitted project to install a pedestrian bridge at Camp Geneva across Lakeshore Dr. between Quincy St. and Riley St. in Park Twp. is slated to close Lakeshore between Quincy and Riley beginning Monday, Sept. 12.

This permitted project is expected to last through Oct. 24.

TRAFFIC IMPACT: Lakeshore Dr. will be closed between Quincy and Riley streets. Traffic will be detoured onto 168th Ave.


Railroad crossing work to close Lakewood Blvd. from Beeline to River

CSX Railroad is scheduled to reconstruct the railroad grade crossing on Lakewood Boulevard west of Beeline Road in Holland Township beginning Monday, Sept. 12.

Lakewood Boulevard will be completely closed off to traffic at the crossing starting Monday, Sept. 12, 2022, and is expected to be closed for one week.

A signed detour for Lakewood Boulevard shall follow Beeline Road north to James Street then west to 144th Ave. (Division) then south to Lakewood Boulevard.

Note: It is anticipated that the River Ave./Lakewood Blvd. intersection will reopen Saturday, Sept. 10.


James St. in Holland Twp. to close Sept. 12-14 for water main work

WHEN: Sept. 12-14

WHERE: James St., 112th Ave. to 120th Ave., Holland Twp.

WHY: Water Main Work

BACKGROUND: A permitted project to install water main connections on James St. between 112th Ave. and 120th Ave. in Holland Twp. is slated to close James St. between 120th Ave. and 112th Ave. Monday, Sept. 12-Wednesday, Sept. 14.

Road Closures

TOWNSHIPSTREETSEGMENTREASONRESPONSIBLE AUTHORITYEST. DURATION
Spring LakePalm Dr.Hickory St. to County LineResurfacingOCRCSept. 30-Oct. 21
Zeeland88th Ave.Gordon St. to Chicago Dr.Force MainPermitSept. 27-Nov. 30
GeorgetownFillmore St.36th Ave. to Taylor St.Culvert ReplacementOCRCSept. 19-Late Oct.
ParkLakeshore Dr.Riley St. to Quincy St.Pedestrian BridgePermitSept. 12-Oct. 21
Olive144th Ave.At Van Buren St.Culvert ReplacementOCRCSept. 6-Oct. 21
HollandBeeline Rd.At Greenly St.Culvert ReplacementOCRCSept. 6-Oct. 7
Georgetown28th Ave.North of FillmoreReconstructPermitMay 24-Oct. 31
Holland/ParkLakewood Blvd.144th Ave. to N. River Ave.Water Main/Reconstruct
More Info
Township/OCRCMarch 18-
Oct. 31
Grand Haven160th Ave.Ferris St. to Lincoln St.Water MainPermitMarch 10-Oct. 15

Road Resurfacing

TOWNSHIPSTREETSEGMENTEST. DURATION
GeorgetownFillmore St./Cottonwood Dr.48th Ave. to Taylor St.Aug. 8-Oct. 31
Spring LakeHickory St./Palm Dr.County Line to 174th Ave.Sept. 30-Oct. 21

Subdivision Resurfacing

TOWNSHIPEST. DURATION